Past Project Highlights

Patterson Blvd Canal Improvements

  • Project consisted of 60,000 sf of new sidealk, 4,000 lf of curb, decorative pavers, monument installation, decorative lighting, and landscaping
  • Supervisor: Tony Donofrio

 WRP Projects, OK NRCS Grant

  • Projects consisted of moving about 200,000 cy of dirt and installation of Water Control Structures
  • Projects completed well of ahead of NRCS Schedule
  • Supervisors: Dale Geuy

 

ODOT 516(11), Pipe Rehabilitation and Liners

  • Project consisted of lining existing CMP with HDPE Pipe of Sizes 108″, 120″ and 132″ along SR 7 near the Ohio River
  • Supervisor: Shane Lipps

 AG-7335-C-11-005, Grant County Bank Stabilization, OK

  • Project consisted of installation of 7,500 tons of rip rap at 7 locations around the county
  • Project completed in 53% of the permitted time
  • Supervisors: Dale Geuy

 

James H. McGee Extension, City of Dayton, OH

  • Projects consists of concrete work including pavement, curb, and sidewalk, excavation, underground storm utilities, electrical and signal work and MOT
  • Project is Currently on going
  • Supervisor: Tony Donofrio

Duck Creek Improvements, Phase 4, USACE

  • Project was finished by Belgray, Inc. after Mainline’s retirement
  • Project included change order work for additional concrete work

The following projects were completed under Mainline Road & Bridge Construction, Inc prior to their retirement.

ODOT 111(02), Greene County, US 35 & North Fairfield Rd Interchange

  • Project involved creating an interchange at US 35 and North Fairfield Road in Beavercreek, Ohio
  • 3 Bridges, extensive MOT, and 500,000 cy of exc/emb
  • Project completed 1 year ahead of schedule
  • Supervisors: Tony Donofrio, Kipp Boone, Shane Lipps

Wright State University Parking Lot Improvements

  • $3 million dollar project
  • Completed in a time frame 2.5 months (between spring and fall quarters)
  • Supervisors: Kipp Boone, Shane Lipps

Riverscape Projects, City of Dayton

  • Project Totals: $8 million
  • Aspects of the projects included dredging the river, landscaping, concrete work, brick pavers, pedestrian bridge, and sheeting
  • Supervisor: Tony Donofrio

South Dixie Pipe Liner Project, Montgomery County, Ohio

  • Lined over 1200 lf of Pipe with HDPE Piping and grout
  • Installed 5 structures and modified outlet structure
  • Supervisors: Shane Lipps, Dale Geuy

Dayton International Airport, Dayton, Ohio

  • Relocated Taxiway C and lengthed Runways 6R
  • Poured over 18,000 sy of concrete pavement (taxiway, runway, roadway)
  • Moved over 100,000 cy of dirt
  • Extensive landscapeing and Beautification including irrigation system
  • Supervisors: Kipp Boone, Tony Donofrio, Dale Geuy

Duck Creek Improvements, Phase 4, USACE

  • Project included installed flood walls along Duck Creek in Cincinnati, Ohio
  • Project consisted of 1.1 million pounds of sheeting, 286 lf of concrete arch, various structures, excavation, roadwork, and storm drainage improvements
  • Project Total: $4.5 million
  • Supervisors: Tony Donofrio, Kipp Boone

Comments are closed.