Patterson Blvd Canal Improvements
- Project consisted of 60,000 sf of new sidealk, 4,000 lf of curb, decorative pavers, monument installation, decorative lighting, and landscaping
- Supervisor: Tony Donofrio
WRP Projects, OK NRCS Grant
- Projects consisted of moving about 200,000 cy of dirt and installation of Water Control Structures
- Projects completed well of ahead of NRCS Schedule
- Supervisors: Dale Geuy
ODOT 516(11), Pipe Rehabilitation and Liners
- Project consisted of lining existing CMP with HDPE Pipe of Sizes 108″, 120″ and 132″ along SR 7 near the Ohio River
- Supervisor: Shane Lipps
AG-7335-C-11-005, Grant County Bank Stabilization, OK
- Project consisted of installation of 7,500 tons of rip rap at 7 locations around the county
- Project completed in 53% of the permitted time
- Supervisors: Dale Geuy
James H. McGee Extension, City of Dayton, OH
- Projects consists of concrete work including pavement, curb, and sidewalk, excavation, underground storm utilities, electrical and signal work and MOT
- Project is Currently on going
- Supervisor: Tony Donofrio
Duck Creek Improvements, Phase 4, USACE
- Project was finished by Belgray, Inc. after Mainline’s retirement
- Project included change order work for additional concrete work
The following projects were completed under Mainline Road & Bridge Construction, Inc prior to their retirement.
ODOT 111(02), Greene County, US 35 & North Fairfield Rd Interchange
- Project involved creating an interchange at US 35 and North Fairfield Road in Beavercreek, Ohio
- 3 Bridges, extensive MOT, and 500,000 cy of exc/emb
- Project completed 1 year ahead of schedule
- Supervisors: Tony Donofrio, Kipp Boone, Shane Lipps
Wright State University Parking Lot Improvements
- $3 million dollar project
- Completed in a time frame 2.5 months (between spring and fall quarters)
- Supervisors: Kipp Boone, Shane Lipps
Riverscape Projects, City of Dayton
- Project Totals: $8 million
- Aspects of the projects included dredging the river, landscaping, concrete work, brick pavers, pedestrian bridge, and sheeting
- Supervisor: Tony Donofrio
South Dixie Pipe Liner Project, Montgomery County, Ohio
- Lined over 1200 lf of Pipe with HDPE Piping and grout
- Installed 5 structures and modified outlet structure
- Supervisors: Shane Lipps, Dale Geuy
Dayton International Airport, Dayton, Ohio
- Relocated Taxiway C and lengthed Runways 6R
- Poured over 18,000 sy of concrete pavement (taxiway, runway, roadway)
- Moved over 100,000 cy of dirt
- Extensive landscapeing and Beautification including irrigation system
- Supervisors: Kipp Boone, Tony Donofrio, Dale Geuy
Duck Creek Improvements, Phase 4, USACE
- Project included installed flood walls along Duck Creek in Cincinnati, Ohio
- Project consisted of 1.1 million pounds of sheeting, 286 lf of concrete arch, various structures, excavation, roadwork, and storm drainage improvements
- Project Total: $4.5 million
- Supervisors: Tony Donofrio, Kipp Boone























